Quick Check Progress Table: Position at 27 July 2010
- Click on the links in the first column of the table below to go the web page for that document. Thid will provide further information on preparation and an opportunity to download current and archived publications as pdf files
Progress on LDF Documents - Quick Check Table
|
LDF Document
|
Completed Stages
|
Current Stage
|
Next Stage
|
|
|
Second revision now published
|
|
|
|
|
SCI submitted to the Secretary of State on 28 June 2005
Inspector's Report Received Feb 2006
|
SCI was formally Adopted on 14th June 2006
|
N/a
|
|
|
Adopted July 2008 |
|
|
|
|
|
Consultation on Combined Scoping Report launched Friday 25th June 2010. Closing date for comments 6th August 2010
|
Appraisal of response to combined Scoping Report Consultation. |
|
|
|
Consultation on Combined Scoping Report launched Friday 25th June 2010. Closing date for comments 6th August 2010
|
Appraisal of response to combined Scoping Report Consultation.
|
Annual Monitoring Report
|
Report published for Financial Year 2008/09 in December 2009
|
Monitoring data being gathered for financial year 2009/10
|
An Annual Monitoring Report (AMR) will be prepared and submitted in December 2010 for the financial year 2009/10
|
Sustainability Appraisal
|
A revised Scoping Document was adopted in March 2007
|
Consultation on revised approach to Sustainability Appraisal launched Friday 25th June 2010. Closing date for comments 6th August 2010.
|
Appraisal of response to consultation and preparation of final revised Sustainability Appraisal Scoping Report.
|
|
Morecambe Area Action Plan
|
Capture Consultation and Scoping Consultation completed |
Consultation on Topic Paper 1 launched Monday 28th June. Closing date for comments 30th August 2010. |
Appraisal of response to consultation. |